Tuesday, February 17, 2009

US-12 Construction Schedule/Open House Set

The initial schedule for the reconstruction of US-12 has been released. construction is scheduled to start April 1 and run through October 9. The following schedule is more a guideline rather then set in stone because of delays that pop up during construction (weather delays, construction problems, etc).

Stage 1- Detour route preparation April 1-15
Stage 2- Reconstruction of the North Main Street Rail crossing April 15-29
Stage 3- Reconstruction of the US-12 Rail Crossing April 30-May 15
Stage 4- South Side Traffic Control, Removal, Underground, and Earthwork May 7-June 15
Concrete/Asphalt Base June 16-June 26
Restoration/Cleanup June 27-July 3
Stage 5- North Side Traffic Control, Removal, Underground, and Earthwork July 6-August 11
Concrete/Asphalt Base August 12-August 21
Restoration/Cleanup August 22-August 28
Stage 6- Driveways/Restoration September 2-September 11
Stage 7- Finish Asphalt and Pavement Markings September 12-September 25
Stage 8- Final Restoration

An Open House will be held on March 11 from 4-7 PM at the Village Hall for anyone looking for more information or with any questions. If you are unable to attend, but have questions, please contact me at any point during this project.